Terminal area: 85,000 m²
Berths: 1
Quay length: 292 m
Draft: up to 14.90 m
Start of construction: 04/2016
Completion: 12/2018
Special feature: 1 berth for jack-up vessels
Operator: Cuxport GmbH
Terminal area: 380,000 m²
Draft: up to 14.90 m
Start of construction: 2025
Completion: 2028
Special feature: Berths 5–7 with a continuous length of up to 1,250 m
Operator: Cuxport GmbH / Blue Water BREB GmbH
Terminal area: 76,800 m²
Berths: 5
Quay length: 737 m
Draft: up to 10.60 m
Start of construction: May 2010
Completion: June 2017
Special features: 2 jack-up berths,
1 RoRo ramp
Operators: Blue Water BREB GmbH Siemens Gamesa Renewable Energy (SGRE)
Draught: 9,50 m – 12,70 m
Terminal space: 116.000 m2
Special feature: 1 RoRo-ramp (1.200 t load capacity)